Project Planning-Developing the project and Determining Critical Path, assignment help

Don't use plagiarized sources. Get Your Custom Essay on
Need an answer from similar question? You have just landed to the most confidential, trustful essay writing service to order the paper from.
Just from $13/Page
Order Now

Project Planning-Developing the project and Determining Critical Path

  • Assignment 2: LASA – Project Planning – Developing the Project Plan and Determining Critical Path

      1. Using the District4WarehouseMove WBS.xls provided, create a Microsoft project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check – District4Move,
        to check your work to be sure you have created your starting project
        plan correctly.  Microsoft Project is required for this task. If you
        have not yet downloaded OpenProj, please click here and follow the directions to do so now.

        Note: you will need to insert a column to include your WBS codes, then
        you will need to sequence the tasks to show tasks by work package. It
        may help to review the Microsoft tutorial, Sequencing tasks in a
        project: http://www.project-open.org/en/project_tutorial

      1. Based
        upon the details in the WBS and the project case, determine which tasks
        need to be completed first and which tasks are dependent upon other
        tasks to be completed prior to starting. Using this information identify
        predecessors in your project plan’s predecessor column. Complete the
        predecessor column by entering the line number of tasks that must be
        completed in order for each task to start. This will create your project
        timeline.

        Note: This is a critical step in the process
        to developing your critical path. It may help to review the Microsoft
        tutorial, Creating relationships between tasks: http://www.slideshare.net/dmdk12/creating-the-network-diagram-and-gantt-with-openproj

    1. Using
      the View Network Diagram functionality within MS Project, determine the
      critical path for this project. In a MS Word document, list the
      activities that are on the critical path. Considering the risks
      identified in the risk table below, identify which risks would be most
      likely to increase your project timeline. Justify your responses.
    2. Submit both your completed project plan and your MS Word document.

    District 4 Production Warehouse Move Project – Risk Table

    1

    Permits are not received per the schedule

    2

    Finish work contractors walk off the job half way through

    3

    Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled

    4

    Work benches are poor quality and 1/3 will have to be rebuilt

    Submit your plan to M3: Assignment 2 Dropbox by Wednesday, December 3, 2014.

    Assignment 2 Grading Criteria

    Maximum Points

    Correctly developed a project plan from the WBS provided

    60

    Completed the predecessor column correctly in the project plan based upon information in the case.

    40

    Correctly identified critical path activities

    16

    Correctly identified risks that would impact the project schedule

    40

    Used
    proper writing components such as, correct grammar, spelling, and word
    choice and cited all sources using correct APA style, etc..

    44

    Total:

    200

     

    Attachments: